Cloud Module Test Platform

Last Updated on : 2020-10-09 07:22:18download

This topic describes how to use the Cloud Module Burning Authorization Platform to carry out production tests accurately, quickly, and reliably. It applies to all Tuya cloud modules.

Prerequisites

  • For the account application, see the PMS SaaS guidance document.
  • Ensure that your system meets the requirements of the installation environment:
    • System: Support only 32-bit or 64-bit Windows 7 or above operating system.
    • Hard disk: The system disk (disk C) reserves more than 200 MB storage space.
    • Memory: More than 1 GB of memory space is required to ensure stable software operation.
    • Processor: Core i5 or above is required to ensure stable software operation.
    • Runtime library: .Net Framework 4.0 runtime library. In general, related libraries are preinstalled in the system.

Download

  1. Log in to the PMS System.

  2. Choose Production Support > Software Download, enter Cloud Module, and then click Search. Among the search results, select, download, and install the Cloud Module Burning Authorization Platform.

Operating procedure

Enter your account number and password, and then click Online Login. You can choose Automatic Login and Remember The Password as needed.

Cloud Module Test Platform

Enter the token

  1. Click Input Token to enter the work order or the token.
    Cloud Module Test Platform

  2. Select Work Order, enter a work order number (Tuya work order or work order created by the customer in the PMS) in the corresponding text box, press the Enter key, and select a station.

    Note: A station can be selected after you press the Enter key. The station content can be displayed only after the process route is maintained.

  3. Select a station from the work order options and then click OK. The following page is displayed.

    Cloud Module Test Platform

  4. Select Token and enter a token in the corresponding text box. Then, select a station.

    Cloud Module Test Platform

  5. Select a station from the token options and then click OK. The following page is displayed.

    Cloud Module Test Platform

File

  1. Click File > Set Up.
    Cloud Module Test Platform

    • Basic Setup:

      • Burn Baud: 1500000 generally (you can set a number according to the actual need).

      • Test Baud: Select a value from the pull-down menu according to the actual need.

      • Only Auth: When the setting is enabled, only authorization is enabled and burning is disabled.

      • Auto Run: You can control automatic running through the fixture DSR instead of clicking manually.

      • Multiple Selection: You can set a value according to the actual needs.

      • Disable Serial: When the setting is enabled, a serial port number cannot be changed manually.

      • End Process: The setting is generally enabled when an Espressif module is tested (Sometimes a test process is stuck and a serial port is locked by an Espressif module). For the other modules, the setting is disabled.

        Cloud Module Test Platform

    • Overall Setup:

      • GPIO/RF Position Test: Before or After means that a GPIO test is conducted before or after burning. If you select Work Order, the item is set by default. If you select Token, the item can be configured.

      • RSSI Test: It refers to the signal strength test. If you select Work Order, the item is set by default. If you select Token, the item can be configured.

      • RSSI Value: If you select Work Order, the item is set by default. If you select Token, the item can be configured.

      • Wi-Fi Hotspot Name: It refers to the 2.4 GHz test router name. After entering the router name, you can find corresponding router signals.

      • Wi-Fi 5G Hotspot Name: It refers to the 5 GHz test router name. After entering the router name, you can find corresponding router signals.

      • Ble Hotspot Name: It refers to the Bluetooth beacon device name. After entering the name, you can find a corresponding Bluetooth beacon.

      • GPIO Test: It refers to the module I/O port test. If you select Work Order, the item is set by default. If you select Token, the item can be configured.

      • SN Check: If you select Work Order, the item is set by default. If you select Token, the item can be configured.

        Cloud Module Test Platform

    • Automation Setup:

      The following parameters are set during the production of an automatic device:

      • Server IP: The IP address of an automatic server.
      • IP Port: The IP port number of an automatic server.
      • Connect Test: Test whether a connection to the server succeeds.
      • Automation: When the setting is enabled, it indicates that an automatic device is used.
      • Pinboard Enablement: When the pinboard is enabled, it indicates that Realtek all-in-one process is used (which is only supported by the RTL8720CF platform).
      • PinboardSet: The pinboard can be configured as follows:

    Cloud Module Test Platform

    Cloud Module Test Platform

    • RF Test:

      • When needed, RF Test is turned on and Cloud enablement is turned on.

      • RF Test Mode: There are two modes, namely itest and IQ. You can select either of them according to the actually used instrument.

      • Test Object: There are two test objects, namely gold plate and non-gold plate. For calibration, the gold plate is preferred. For normal tests, the non-gold plate is preferred.

      • In the itest mode, the instrument is set as follows:

        • Instrument Type: WT-208.
        • Instrument SN: Fill in the serial number of your instrument.
        • Line Loss Calibration: Select RF1 if 1 to 4 ports of an iTest instrument are used, and select RF5 if 5 to 8 ports are used.
        • Origin RF Port: Select 1 if 1 to 4 ports of an iTest instrument are used, and select 5 if 5 to 8 ports are used.
        • Gold Plate Number: Fill in WB3L-1 if WB3L and No. 1 gold plate are used, and fill in WB3L-2 if WB3L and No. 2 gold plate are used, and so on.
        • Instrument IP: The actual IP address of an iTest instrument.
        • Local host: The IP address of a network port through which the computer is connected to an iTest instrument.
        • COM and RF Port: You can select according to your actual settings.
        • Server Port and Client Port: You can set as follows.

        Cloud Module Test Platform

        Cloud Module Test Platform

      • Settings of an IQ instrument are as follows:

        • Instrument Type: IQ2010.
        • Instrument SN: Fill in the serial number of your instrument.
        • Line Loss Calibration: Select RF1 when calibrating No. 1 port, and select RF2 when calibrating No. 2 port.
        • Gold Plate Number: IQ-Product Number-Number. For example, if the gold plate label of WR3 is IQ-1, the gold plate is numbered as IQ-WR3-1.
        • A COM port must correspond to an RF port one by one.

        Cloud Module Test Platform

        For more information about gold plate calibration, see the Guide of Gold Plate Calibration.

    • Functional settings:

      • Station Check: When Station Check is used to detect the current station status of SN, all detected stations will become red and repeated check is prohibited.

      • Code Scanning Trigger: You can start a program by scanning a code.

      • Esp Pre Burn: When an Espressif module fails in a GPIO test and it is determined that the firmware is not supported, you can enable Esp Pre Burn.

      • Select a folder where the firmware is located and select firmware of the corresponding model to carry out a normal test. Pre burning will be conducted to test the GPIO functions, and then a normal burning authorization process is carried out.

      • Serial port ID display: When a serial port setting tool is used to lock a serial port ID, the setting must be enabled to display the port ID of the tool.

        Cloud Module Test Platform

    • Pack Set

      • Automatic tape wrapping: If the setting is enabled, Tuya visual package is used.

      • Packaging relay control: When the Tuya visual package is used, the setting must be enabled to control the relay of foot pedals of a packaging machine.

      • Relay custom protocol: It is temporarily reserved and not used.

      • QR Direction Detection: When the setting is enabled, the PCBA placement direction is detected to avoid incorrect placement directions.

      • Direction to be detected: Select the direction according to the sticking direction of the QR code.

      • For Tuya visual package, see Tape Visual Operation Manual.

        Cloud Module Test Platform

  2. Click File > Logout to log out of the current account.

Local

Click Local to view the passing rate of each channel currently. The data can only be viewed locally. It can be reset to 0.

Cloud Module Test Platform

Token Replacement

  1. After the token replacement is carried out in the PMS system, you need to conduct a test to replace the token. For more information, see Operation Manual of PMS Platform—SAAS.

    Cloud Module Test Platform

  2. Click TokenReplacement, enter the token, and then select a station.

    Cloud Module Test Platform

Help

  1. Click Help > Language to switch between English and Chinese.

    Cloud Module Test Platform

  2. Click Edition to view updated information about the current version.

Page composition

  • Basic information: It shows related information about the current work order or token.
    Cloud Module Test Platform

    Cloud Module Test Platform

  • Run: When Auto Run is enabled, you need to click Run and press a fixture down to start a test. When Auto Run is disabled, you need to click Run to start a test.

    Cloud Module Test Platform

  • Com Port, SN and DSR: The com port is set to be a serial port connected to the current device. SN is the serial number on the product label. If DSR is 0, it indicates that the fixture press-down status is not detected. If DSR is 1, it indicates that the fixture press-down status is detected. The arrow in the following picture indicates the press-down and rise-up status.

    Cloud Module Test Platform

  • Running Page, Test Details, and Error Details: Before a test, a page is ready. When a test starts and an item fails, you can click to view Error Details to analyze problems. With Test Details, you can view each test item and test time.

    Cloud Module Test Platform

  • When a test succeeds, the page will prompt Success and turn into green. At the bottom right corner, you can view the total test time of the current tool.

    Cloud Module Test Platform

Things to note

  • To log in, you must use an account with the work order or token operation permission. If not, a test cannot be performed normally.
  • To configure different types of products and production methods, see the standard operating procedure.
  • The replaced token must be applied to the token replacement test, rather than a normal production test process.
  • After the Auto Run is enabled, click Run and then press the fixture. Otherwise, the tool will not respond.
  • When performing a multi-channel test, the corresponding port numbers must be a one-to-one correspondence. Otherwise, tokens will be authorized to wrong port numbers.
  • When using the work order test or token to enable the SN detection, you must enter the SN. Otherwise, it will prompt that the SN does not exist.
  • When the DSR displays 0 after the fixture is pressed down, check the fixture and the wiring, and check whether the tool is running.